Project Details

  • Location:

    HG Construction Freewharf Phase 2 Shoreham on sea

  • Details:

    The design and construction of 143 Residential Flat and associated communal amenitiy areas, basement, cycle store, external landscaping, river walkway

About the Project

Phase 2.- 143 Residential Flat .

Key Points of contract.

  • ReadyLock System used to omit ledger bracing and enable us to reduce the program by 8 weeks per block.
  • Full time non - working supervisor to safely co-ordinate working areas over the 2 blocks, and monitor quality control.
  • we consistently ahead of program.
  • 98% Safety score achieved every month.
  • every board had to be clipped & every lift was fitted with internal guardrails, demonstrating good practice.
  • Top three sub contractor on site every month
WSCL Hg Construction Image 4
WSCL Hg Construction Image 5
WSCL Hg Construction Image 6
get in touch

Contact Us Now

To work with a new scaffolding company within a 70 mile radius of Solent Business Centre, Southampton, you’re in the right place. Give us a call today and we can discuss your project in greater detail.